View of the Duwamish Waterway from Terminal 115

Timeline

Historical image of Boeing Plant 1 from 1918

Boeing Plant 1 (1918)

1916

Boeing Plant 1 Facility opens

1970

Port of Seattle purchases Terminal 115

1993

T-115 Site listed by Department of Ecology

2015

Port of Seattle and Boeing listed as Potentially Liable Parties

2020

Agreed Order between the Port, Boeing, and Ecology

2022

Development of Remedial Investigation Work Plan begins

Three people working at a table with soil samples and tools

Soil sample processing during August 2024 sonic drilling activities

2024

Remedial Investigation fieldwork begins

2025

Anticipated completion of Remedial Investigation fieldwork

2027

Anticipated approval of Remedial Investigation/Feasibility Study

2028

Anticipated publication of draft Cleanup Action Plan

2029 - 2031

Prepare for design, permitting, and implementation of the cleanup plan